Windows and doors update

You are viewing an old revision of this post, from October 9, 2013 @ 07:02:22. See below for differences between this version and the current revision.

Phase 2 began with assembly of materials and equipment during the week of September 16. Actual installation of new windows and doors began September 23. The contractor is working on installing windows and balcony doors on the South side, facing the parking garage. That work should be completed by mid-October.

The second stage of Phase 2 will follow with new windows and doors installed on the West side, facing the visitors’ parking lot.

Schedules have been posted in the building. If you’re not on site and would like a schedule, please contact me.

– Doug Brandy, Director

Post Revisions:

Changes:

There are no differences between the October 9, 2013 @ 07:02:22 revision and the current revision. (Maybe only post meta information was changed.)