At the April 17 meeting owners raised a number of questions about the windows project. Representatives from the Board, engineering consultants and the installer provided responses.

  • How will problems with sliders be corrected? New sliders will be manufactured and defective ones will be replaced.
  • How can we be confident new windows will meet our expectations? The Board has hired an independent engineering firm to do extensive laboratory and on-site testing on new windows before they are installed.
  • The “final inspection” scheduled for April 17 was not completed. When will it resume? It was an error to identify this inspection as “final”. Representatives of the Board and the installing contractor completed inspection of installed windows and balcony doors on April 24.