Bruce Kenny, Senior Project Manager, Infrastructure Services Department, City of Ottawa provided answers to these questions:

Q: When will the roadway leading to the Lycee be closed?

A: The closure of Old Riverside Drive on each side of the Hospital Link is expected to be closed in mid June 2016 based on our current schedule.  We would like to wait until the end of the school year however the closure date is linked to some important railway bridge construction work which cannot be delayed.

Q: When do you anticipate that the city will have our section of the Frobisher road repaired and resurfaced?

A: The resurfacing of Frobisher is outside of the scope of the Hospital Link project which is funded from development funds.

Post Revisions:

Changes:

May 2, 2016 @ 12:47:16Current Revision
Content
Unchanged: <p class="ecxMsoNormal">Bruce Kenny, Senior Project Manager, Infrastructure Services Department, City of Ottawa provided answers to these questions:</p>Unchanged: <p class="ecxMsoNormal">Bruce Kenny, Senior Project Manager, Infrastructure Services Department, City of Ottawa provided answers to these questions:</p>
Deleted: <p class="ecxMsoNormal"></p> 
Unchanged: <p class="ecxMsoNormal">Q: When will the roadway leading to the Lycee be closed?</p>Unchanged: <p class="ecxMsoNormal">Q: When will the roadway leading to the Lycee be closed?</p>
Unchanged: <p class="ecxMsoNormal">A: The closure of Old Riverside Drive on each side of the Hospital Link is expected to be closed in mid June 2016 based on our current schedule.  We would like to wait until the end of the school year however the closure date is linked to some important railway bridge construction work which cannot be delayed.</p>Unchanged: <p class="ecxMsoNormal">A: The closure of Old Riverside Drive on each side of the Hospital Link is expected to be closed in mid June 2016 based on our current schedule.  We would like to wait until the end of the school year however the closure date is linked to some important railway bridge construction work which cannot be delayed.</p>
Unchanged: <p class="ecxMsoNormal">Q: When do you anticipate that the city will have our section of the Frobisher road repaired and resurfaced?</p>Unchanged: <p class="ecxMsoNormal">Q: When do you anticipate that the city will have our section of the Frobisher road repaired and resurfaced?</p>
Unchanged: <p class="ecxMsoNormal">A: The resurfacing of Frobisher is outside of the scope of the Hospital Link project which is funded from development funds.</p>Unchanged: <p class="ecxMsoNormal">A: The resurfacing of Frobisher is outside of the scope of the Hospital Link project which is funded from development funds.</p>
 Added: <p class="ecxMsoNormal"><a href="http:// frobisherplace.ca/ avhl-night-work/" target="_blank">Related info.</a></p>